WAR-132-10.15 Bridge Replacement - Construction Testing Location: Shale and existing roadway materials excavated on site were compacted with a sheep-foot compactor before being utilized in embankment placement. The materials were inspected for stability and tested for degrees of moisture and compaction. As needed, the inspector regulated the addition of dry materials to bring the fill to optimum moisture levels. Moisture density samples were sent to the lab for testing. During the pour process, concrete cylinder samples were taken and transported to our testing laboratory for curing and break testing. Our inspectors produced written field reports for each site visit, logging the day’s activities and testing results. |